Tram
Gubacsi út bridge
Budapest · 2021 · Locomotive CEE Kft.
View projectTram

Our client on this job was Budapest Közút Zrt., and we carried out the work together with Hunholz Kft. We had to dismantle the disused pipe bridge structure that had long spoiled the Budapest skyline. As part of this complex task, we dismantled 350 m of the BKV Zrt. overhead line network and its support wires for the duration of the bridge crane lift. The crane work was carried out by Koós Wéber Kft.; after the lift we restored the network to its original condition. Before lifting the bridge out in one piece, we reinforced the structure in line with the structural design. Berkó & Berkó Speciál Transport Kft. removed the bridge from the site; afterwards, at our client's request, we cut it up and delivered it to their premises.
Tram overhead line dismantling and reinstatement for the FŐTÁV bridge demolition: clearing the crane work area, then rebuilding the network.